Oconee - What is your longest standing (Licensing Required and NEIL) impairment and what is keeping you from getting it fixed?

Farley -  VESDA Obsolete Detection system- 450 days old - Waiting on Mod

Hatch - Broken Diesel Driven Fire pump - 200 days old - Waiting on Mod to replace this engine

Vogtle 1/2 - NSCW tower detection system - 300 days - No Maint. resources, getting contractor to replace

Vogtle 3/4 -  Detection / Automatic Suppression not installed yet in Spent Fuel Pull, waiting on completion of new system installation and turnover

Watts Bar - Electric fire pump OOS due pressure control valve - design issue to replace current valve

Sequoia -  Multiple NEIL impairments with three NEIL impairments back to 2013 but no licensing required impairments, need funding for NEIL impairment repair

Browns Ferry - Supervision Alarms (Pre-action system) failures - greater than 450 days - funding and management priority

North Anna - Simplex panel detection system card issue - greater than 450 days - needs ED for obsolete part but have positive path forward to closure

Surry - Hose House in PA with supply piping failed due to graphic corrosion - 500 days - Lingering repair and lack of ownership - developed fire protection excellence team and real improvement in old impairments noted since

St. Lucie -  Obsolete and degraded FP detection panels and ECCS detection system field devices - open since 2013 due to lack of funding and priority, changed Work Management Process and have funding now and impairments are on track for closure in near future

McGuire - Detection system OOS (NEIL) due to notification system failure - 6 months, lack of funding and plant priority

Brunswick -  Drain system failure to handle multiple system actuation in short time period due to drain blockage, 2550 days, complexity and plant prioritization, on track for closure next outage

Oconee -  Multiple hydrant issues, oldest is 2000 days, complexity of repair, rework and work prioritization

Harris - No comment

Catawba - Detection failures in containment - 330 days (Outage required) - Outage require for repair

Robinson - No long term impairments (have Fire protection oversight committee, work prioritization and MFIN team repairing with urgency)

VC Summer - No long term impairments